Ladder Logic (Parallel SS/FF Relationships) in Microsoft Project

Microsoft Project does not allow users to create multiple logical relationships between the same two tasks.  Project DOES ALLOW importing of such multiple relationships in XML files, however.  If desired, users can directly edit XML versions of project schedules to introduce multiple logical relationships, and these relationships appear to be persistent and active in all … Continue reading Ladder Logic (Parallel SS/FF Relationships) in Microsoft Project