No Summary Tasks on the Critical Path – Calculating Total Slack for Summary Tasks in Microsoft Project

Total Slack as presented in Microsoft Project is not a valid metric for logical analysis of Summary Tasks.  Users are advised to ignore it. Underlying the “automatic” project scheduling in Microsoft Project are some simple mathematical processes that are commonly referred to as the Critical Path Method (CPM).  CPM schedule calculation starts with a “Forward-Pass” … Continue reading No Summary Tasks on the Critical Path – Calculating Total Slack for Summary Tasks in Microsoft Project