Driving Logic in Backward Scheduled Projects (Microsoft Project)

In MSP, a “backward scheduling” mode – sometimes called backward planning, reverse scheduling, or reverse planning – can be invoked by scheduling the project from its finish rather than its start.  In the traditional language of Critical Path Method scheduling, it’s most simply described as a Late Dates schedule.  Backward planning is useful in several non-standard methodologies, including Critical Chain Project Management and the “Pull Planning” aspects of the Last Planner System.

The Mechanics of Backward Scheduling

When specified for the active project, this mode essentially does the following:

  1. Sets the default constraint type for all new tasks to As Late As Possible.
  2. Re-sets the constraint type for all existing Summary tasks to As Late As Possible.
  3. [Users choosing this mode in the middle of schedule development must manually re-set the constraint type for all existing non-Summary tasks to As Late As Possible.]
  4. Automatically sets “No Later Than” constraints when dates are manually entered into the Start or Finish fields of tasks.  [Such date entry in forward scheduling mode leads to “No Earlier Than” constraints, so users choosing this mode in the middle of schedule development should manually review, validate, and potentially re-set any previously-entered date constraints.]
  5. Performs the network scheduling calculations in reverse order, with the reflection point occurring at the project start rather than the project finish.  I.e. the Project Start Date (not the Finish, which is user-input) is determined by the logic.
  6. Sets the “Start” and “Finish” of automatically-scheduled tasks to their Late Dates rather than their Early Dates.  (This is the most important part.)
  7. Finally, the resource leveling engine resolves resource over-allocations by accelerating higher priority tasks from late dates rather than delaying lower priority tasks from early dates.  Thus, entries in the “leveling delay” field are negative.  This behavior creates a minor complication regarding use of Priority = 1000.  Just as in forward scheduling, a task with Priority=1000 is always exempted from any leveling action.  In backward scheduling, this means that Priority values of 1000 and 0 are essentially equivalent when considered in the leveling decisions.  The highest effective Priority for controlling leveling behavior then becomes 999, not 1000.

Logic relationships used in backward scheduling still have exactly the same meanings that they do in forward scheduling.  A Finish-to-Start relationship still means that the two tasks are logically connected such that the successor may not start before the predecessor finishes, and the rarely-applicable Start-to-Finish relationship still indicates that it is impossible for the successor to finish before the predecessor starts.  Some users seem to think that backward scheduling involves reversal of these two relationships in particular, but that’s not consistent with the rest of the backward scheduling mode.  Unfortunately, mixing of the two approaches seems to continue, though this typically amounts to invalid date manipulation in my view.

In normal (i.e. forward) scheduling, a task with an “As Late as Possible” constraint has the dubious distinction of corrupting its entire chain of successors – driving all of them to the critical path.  There are very few legitimate applications for this constraint.  In backward scheduling, the “As Soon as Possible” constraint plays a similar role, corrupting its chain of predecessors.  It needs to be avoided in backward scheduling.

When to Use Backward Scheduling

I’ve never used backward scheduling in a real project.  Others have recommended its use to determine the desired start date of a project when the desired completion date is already known.  It also seems consistent, when tasks are suitably buffered, with aspects of Critical Chain Project Management that require work to be scheduled as late as possible.

Ultimately, backward scheduling rests on the presumption that tasks can be accelerated (i.e. moved to the left on the bar chart) indefinitely as needed to meet the fixed end date for the project.  Thus, a task whose duration is extended can simply be re-scheduled to start sooner than previously planned, with its predecessors also being accelerated.  Similarly, a higher priority task can be started (and finished) earlier to avoid resource conflicts with a lower-priority task that demands the same resources.  The problem with these presumptions is that time invariably marches forward, and as scheduled dates for incomplete work are overtaken by the vertical time-now line on the bar chart there is no chance for recovery.  The backward scheduling method is pointless if the latest allowable Project Start Date has already been passed – e.g. the project is in progress.

Backward scheduling seems to be of primary value in determining the latest responsible date to start a project (or project segment) while still meeting the desired completion date.  After that, the project must be converted from backward-scheduled to forward-scheduled mode if it is to be used for updating and forecasting during project execution.  The original question – i.e. what is the latest responsible project start date? – is also easily answered by manipulating and examining the late dates of the forward scheduled project.  Thus, for a competent project scheduler, the use of backward scheduling seems largely to be an unproductive diversion.

Driving Logic Analysis

When the logic network is well constructed – and complicating factors like multiple calendars, (Early) constraints, and resource leveling are avoided – then the Critical Path may be reasonably identified by Total Slack = 0.  Other methods of driving logic analysis must be modified, however.

Under Backward Scheduling, any slack/float of a task exists on the side towards its predecessors, i.e. to its left on a bar chart.  A driving relationship exists when a successor prevents a predecessor from being scheduled any later than it is.  This means that there are Driving Successors and Driven Predecessors.  Consequently, the Longest Path in a backward scheduled project is the Driving (Successor) Path from the Project’s Start.

MSP includes two built-in methods for reviewing and analyzing driving logic: the Task Inspector and the Task Paths bar styles.  As I wrote in this article a few years ago, I’ve found these tools to be unreliable in complex real-world project schedules.   Under backward scheduling, they are essentially useless and/or misleading.

To start with, Task Inspector simply doesn’t work with backward scheduling.  Opening TI on a backward scheduled project yields the following message:  This project is set to Schedule from Finish.  We are unable to provide scheduling information.

Also under backward scheduling, the “Driving Predecessors” and “Driven Successors” bar styles are still derived from Early Dates, as they are in Forward Scheduling.  This makes them essentially useless for assessing the controlling logic of the displayed (Late Dates) schedule.  Consider the example below, where all four Task Path bar styles have been imposed, and Task 11 – A2 Structures – is selected.  (The automatic “Slack” bar style is also imposed, but it is invisible since Free Slack – formally defined by Early dates alone – is uniformly zero.) 

The selected task is in fact driving/controlling the displayed dates of both of its predecessors, but only one of them displays the correct bar style (the one that was the driving predecessor during the forward pass).  Of Task 11’s four successors, only the first (Task 13 – A2 Electrical) is directly driving/controlling Task 11’s schedule.  The tasks for two of the remaining three successor relationships are incorrectly highlighted, while the third (Task 14) is correctly highlighted only because it is driving/controlling Task 13 – a case of redundant logic.  (All four successors were driven successors during the forward pass.)  Thus in a backward scheduled project, the Task Path bar styles for Driving and Driven dependencies are meaningful (or “correct”) ONLY along the Longest/Critical path of the project, where Early dates and Late dates coincide.

BPC Logic Filter – my company’s Add-In for logic analysis of MSP schedules – identifies driving logic based on relationship free float, which we often call “relative float.”  In BPC Logic Filter, the Longest Path and near-longest paths of simple, backward-scheduled projects can be found using the Task Logic Tracer, starting from the project start milestone and using appropriate settings (i.e. driving relationships in successor direction).  As illustrated in the example project, this is fairly trivial since the results are 100% aligned with Total Slack. 

Other driving logic paths (not on the Critical Path) are not so trivial but are easily addressed using BPC Logic Filter, provided that the impact of multiple calendars is minimal.

Precision analysis of more complex, backward-scheduled projects requires some modest modifications to the algorithms.  In particular, several variations of late-relationship-float need to be computed, and these have been added to the development roadmap for the software.

What is the Longest Path in a Project Schedule?

In Project schedules, the Longest Path yields the Shortest Time.  Aside from the mental gymnastics needed to digest that phrase, the concept of Longest Path – especially as implemented in current software – has deviated enough from its origins that a different term may be needed.   

Critical Path as Longest Path

Authoritative definitions of the “Critical Path” in project schedules typically employ the words “longest path,” “longest chain,” or “longest sequence” of activities … (that determine the earliest completion date of the project.)  In other words, the path, chain, or sequence with the greatest measured length is the Critical Path.  As a rule, however, none of the associated documents are able to clearly define what constitutes the length of a logic path, nor how such length will be measured and compared in a modern project schedule.  Without a clear standard for measuring the length of something, explicitly defining the Critical Path in terms of the longest anything is just sloppy in my view.

The Original Path Length

Assessing path length used to be much easier.  In the early days of CPM (Critical Path Method) scheduling, any project schedule could be guaranteed to have ALL Finish-to-Start relationships, NO constraints, NO lags or leads, NO calendars, and only ONE Critical Path.  Under these conditions, the length of a logic path could be clearly defined (and measured) as the sum of the durations of its member activities.  Thus, the overall duration of a Project was equal to the “length” (i.e. duration) of its Critical Path, which itself was made up of the durations of its constituent activities.  That result is indicated in the figure below, where the 64-day project length is determined by the durations of the 5 (highlighted) activities on the Critical Path.  Adding up the activity durations along any other path in the schedule results in a corresponding path length that is less than 64-days – i.e. not the “longest” path. [The network diagram was taken from John W. Fondahl’s 1961 paper, “A Non-Computer Approach to the Critical Path Method for the Construction Industry,” which introduced what we now call the Precedence Diagramming Method.  Unfortunately, Microsoft Project (MSP) has an early limit on dates, so his presumed ~1961 dates could not be matched.]

Fortunately, in such simple projects, it’s never been necessary to aggregate and compare the lengths of every logic path to select the “longest path.”  The CPM backward pass calculations already identify that path by the activities with zero-Total Float/Slack, and successively “shorter” paths are identified by successively higher Total Float/Slack values.  This fact has been verified in countless student exercises involving simple project schedule networks, typically concluding with the axiom that “the Critical Path equals the longest path, which equals the path of zero-Total Float/Slack.”

Float/Slack and Path-Length Difficulties

In general, modern complex project schedules have, or can be expected to have, complicating factors that make Total Float/Slack unreliable as an indicator of the Critical Path – e.g. non-Finish-to-Start relationships, various early and late constraints, multiple calendars, and even resource leveling.  See this other article for details.  Therefore, as noted earlier, the axiomatic definition has been shortened to “the Critical Path equals the longest path.”

Unfortunately, finding the “longest path” by arithmetically summing the activity lengths (i.e. durations) along all possible logic paths and comparing the results – not easy to begin with – has gotten more difficult.  Lags, excess calendar non-working time, early constraints, and resource leveling delays all add to the true “length” of a logic path compared to the simple summation of activity durations.  On the other hand, leads (negative lags), excess calendar working-time, and the use of overlapping-activity relationships (e.g. SS/FF) reduce its length.  In addition, any hammocks, level-of-effort, and summary activities need to be excluded.  All such factors must be accounted for if the “longest path” is to be established by the implied method of measuring and comparing path lengths in the project schedule.  I don’t know of any mainstream project scheduling software that performs that kind of calculation.  Alternatively, Deep Schedule AnalysisTM using the proprietary HCP (Hidden Critical Path) Method – from HCP Project Management Consulting – appears to compute and compare the lengths of all logic paths in Primavera and MSP schedules.

Longest Path as Driving Path

Contrary to summing up and comparing logic path lengths, current notions of the “longest path” are based on an approach that does not involve path “length” at all.  As a key attribute, the longest path in a simple, un-progressed project schedule also happens to be the driving logic path from the start of the first project activity to the finish of the last project activity.  It is a “driving logic path” because each relationship in the path is “driving”, that is it prevents its successor from being scheduled any earlier than it is.  Driving relationships are typically identified during the forward-pass CPM calculations.  Subsequently, the driving path to the finish of the last activity can be identified by tracing driving logic backward from that activity, terminating the trace when no driving predecessors are found or the Data Date is reached.  The resulting driving path to project finish is also called the “longest path” even though its “length” has not been established.  This is the “Longest Path” technique that has been applied for nearly two decades by (Oracle) Primavera and adopted more recently in other project scheduling tools.

As of today, MSP continues to define Critical tasks on the basis of Total Slack, but it provides no explicit method for identifying the “Critical Path” using a “longest path” criterion.  How is the responsible MSP scheduler supposed to respond to a demand for the “critical path” when the longest path has been obscured?  Here are several options:

  1. Continue to make simple projects, avoiding all complicating factors like calendars (including resource calendars), early and late constraints, deadlines, and resource leveling. Then assume that “Total Slack = 0” correctly identifies the Critical Path.
  2. If you are using MSP version 2013 or later,
    • Ensure that your project is properly scheduled with logic open-ends only present at a single start and single finish task/milestone, then select the single finish task,
    • Try to use the “Task Path” bar highlighter to highlight the “Driving Predecessors” of your selected finish task.  In the example below, a Deadline (a non-mandatory late-finish constraint) has been applied to task Op12 in the 1961 example, and MSP has responded by applying the “Critical” flag (based on TS=0) to Op12 and its predecessors Op10 and Op2.  As a result, the Critical Path is obscured.  Applying the bar highlighter and selecting task Op18 (the project’s finish task) correctly identifies the driving path to project completion, i.e. the “longest path.”  (For clarity, I manually added the corresponding cell highlighting in the table; the bar highlighter doesn’t do that.)
    • If necessary, create and apply a corresponding filter for the highlighted bars. I’ve posted a set of macros to make and apply the filter automatically in this article.
  3. If you are using MSP version 2007 or later,
    • Ensure that your project is properly scheduled with logic open-ends only present at a single start and single finish task/milestone, then select the single finish task,
    • Try to use the Task Inspector to identify the driving predecessor of the selected task, then go to it and flag it as being part of the driving path. Repeat this until the entire driving path is marked.
    • If necessary, create and apply a filter and/or highlighting bar styles for the flagged tasks.
    • I’ve posted another set of macros to do all this (except bar highlighting) automatically in this other article.
  4. Note: The previous two approaches both rely on MSP’s StartDriver task object to identify driving relationships. As noted in this article, however, the resulting driving logic is not reliable in the presence of tasks with multiple predecessors, non-FS predecessors, or actual progress.
  5. Use BPC Logic Filter or some other appropriate add-in to identify the “longest path” in the schedule.

Whichever method or software is used, expressing the Longest Path using the Driving Path methodology has one key weakness: it has not been proved generally useful for analysis of near-critical paths.  While the Longest Path may be known, its actual length is not readily apparent.  More importantly, there is no basis for computing the lengths, and hence the relative criticality, of the 2nd, 3rd, and 4th etc. Longest Paths.  Consequently, Near-Critical paths continue to be identified based on Total Float/Slack, which is still unreliable, or – in P6 – based on unit-less “Float Paths” from multiple float path analysis.

“Longest Path” and Early Constraints

As noted several times here, the methods described for identifying the “longest path” are in fact describing the “driving path to the project finish.”  This distinction can raise confusion when an activity is delayed by an early constraint.  Consider the case below, where an activity on the longest path (Op13) has been delayed 2 days by an early start constraint.  Consequently, its sole predecessor relationship (from Op3) is no longer driving, and Op3 gains 2 days of Total Float/Slack.  As shown by MSP’s “Driving Predecessor” bar highlighter, the driving logic trace is terminated (going backwards) after reaching the constrained task.

Identical results are obtained from Primavera’s (P6) Longest Path algorithm.  This is neither surprising nor incorrect; the project’s completion is in fact driven by the external constraint on Op13, and its predecessor Op3 is quite properly excluded.

It’s clear therefore that the driving path to project completion and the longest path from the project start (or Data Date) to the project completion can differ when an early constraint is present.  P6’s “Longest Path” algorithm automatically defaults to the driving path, not the actual longest path, and to date there have been no built-in alternatives to that behavior.  As a result, some consultants suggest that P6 Longest Path analyses should be rejected when external constraints – even legitimate ones like arrival dates for Customer Furnished Equipment – are present.  (A P6 add-in, Schedule Analyzer Software, does claim to provide a true Longest Path representation in the presence of early constraints.)

BPC Logic Filter – Longest Path Filter

BPC Logic Filter is a schedule analysis add-in for MSP that my company developed for internal use.  The Longest Path Filter module is a pre-configured version of the software’s Task Logic Tracer.  The module is specifically configured to identify the project’s longest path (as driving path) through the following actions:

  1. Automatically find the last task (or tasks) in the project schedule.
    • Excluding tasks or milestones that have no logical predecessors. (E.g. completion milestones that are constrained to be scheduled at the end of the project but are not logically tied to the actual execution of the project. The resulting trace would be trivial.)
    • Excluding tasks or milestones that are specifically flagged to be ignored, e.g. (“hammocks”)
  2. Trace the driving logic backwards from the last task to the beginning of the project.
    • Driving logic is robustly identified by direct computation and examination of relative floats. (Driving relationships have zero relative float according to the successor calendar.)  The unreliable StartDriver task objects are ignored.
    • Neither completed nor in-progress tasks are excluded from the trace.
  3. Either apply a filter to show only the driving logic path, or color the bars to view the driving logic path together (in-line) with the non-driving tasks. The example below is identical to the previous one, but BPC Logic Filter formats the bar chart to ignore the impacts of the applied deadline.  The resulting in-line view is substantially identical to the bar chart of the original, unconstrained project schedule. 

BPC Logic Filter and the (True) Longest Path

As noted earlier, an early constraint can truncate the driving path to project completion.  In that case, it is debatable in my view whether the addition of non-driving, float-possessing activities into the “longest path” makes that term itself more or less useful with respect to the typical uses of the “Critical Path” in managing and controlling project performance.  Nevertheless, such an addition is easily allowed in BPC Logic Filter by checking a box.  The bar chart below shows the results of the Longest Path Filter on the early-constrained example schedule, as set up according to the driving-path (Primavera) standard.  Results are identical to those of the built-in “Driving Predecessors” highlighter in MSP (above) and of P6.

The next chart shows the complete “longest path” for the project, including the non-driving Op3 activity.

The second chart is different because the check box for “Override if successor task is delayed by constraint” has been checked in the analysis parameters form.  Checking the box causes the non-driving predecessor with the least relative float to be treated as driving, and therefore included in the Longest Path, in the event of a constraint-caused delay.

For a quick illustration, see Video – Find the Longest Path in Microsoft Project Using BPC Logic Filter.

BPC Logic Filter and Near Longest Paths

As noted earlier, the normal methods for identifying the “longest path” (i.e. the driving path) in a project schedule have not been generally adopted for analyzing near-longest paths.  P6 offers multiple float path analysis, which I wrote about here.  In addition,  Schedule Analyzer (the P6 add-in mentioned earlier) computes what it calls the “Longest Path Value” for each activity in the schedule – this is the number of days an activity is away from being on the Longest Path (i.e. the driving path to project completion.)   In the absence of demonstrated user demand, however, MSP seems unlikely to gain much beyond the Task Path bar highlighters.

BPC Logic Filter routinely computes and aggregates relative float to identify driving and near-driving logic paths in MSP project schedules.  In this context, “near-driving” is quantified in terms of path relative float, i.e. days away from driving a particular end task (or days away from being driven by a particular start task.)  Its “Longest Path” and “Near Longest Path” analyses are special cases where the automatically-selected end task is the last task in the project.  For the Near Longest Path Filter, tasks can be shown in-line (with bar coloring) or grouped and sorted based on path relative float.  The “override if successor is delayed by constraint” setting has no effect when the Near Longest Path Filter is generated.  In that case, the non-driving task will be displayed according to its actual relative float.  For example Op3 is shown below with a relative float of 2 days (its true value), not 0 days as shown on the earlier Longest Path Filter view.

Recap

  1. In the development of the Critical Path Method, the “longest path” originated as one of several defining characteristics of the “Critical Path” in simple project schedules. Specifically, the “Critical Path” included the sequence of activities with the highest aggregated duration – i.e. the “longest path”.  Actual computation and comparison of path lengths was not necessary since relative path lengths could be inferred directly from Total Float – a much easier calculation.
  2. Complicating factors in modern project schedule networks tend to confuse the interpretation of Total Float, such that it is no longer a reliable surrogate for path length. As a result, the most recent, authoritative definitions of the Critical Path typically omit references to float while retaining references to “longest path” and, typically, logical control of the project completion date.  [Notably, the measurement and comparison of aggregated path durations (path lengths) has not been an explicit feature of any mainstream project scheduling tool, so the “longest-path” part of the definition cannot be definitively tested in general practice.]
  3. Notions of “longest-path” among current schedule practitioners are heavily influenced by the deceptively-named “Longest Path” feature in Oracle/Primavera’s P6 software. Perversely, that feature DOES NOT aggregate activity durations along any logic paths.  Rather, it identifies the driving/controlling logic path to the project’s finish.
  4. The “Longest Path” in P6 (i.e. the Driving Path to Project Completion) and the “longest path” (i.e. the logic path with highest aggregated duration) are NOT equivalent, particularly when the “Longest Path” is constrained by an early date constraint. There is at least one P6 add-in claiming to identify the true “longest path” (and near-“longest paths”) in this case.
  5. Microsoft Project provides several inefficient methods to identify the Driving Path to Project Completion in simple projects, but these methods are not reliable in the presence of non- Finish-to-Start relationships. There are no native MSP methods for identifying near-driving tasks nor the true “longest path” in the presence of early date constraints.  BPC Logic Filter is an MSP add-in that automatically fills these gaps.
  6. As conceived, the “longest path” criterion implied the transparent calculation and comparison of aggregated activity durations along each logic path in a project schedule. As for Total Float, however, such calculations in complex schedules have been obfuscated by complications like non- Finish-to-Start relationships, lags, and multiple calendars.  Since such obfuscation makes path lengths essentially un-testable, it appears that future Critical Path definitions should omit the “longest path” criterion in favor of a simple “driving path to project completion.”

Longest Paths in Backward Scheduled Projects (MSP) [Jan’19 Edit]

As pointed out in this recent article, the Longest Path in a backward scheduled project is essentially the “driven path from the project start,” not the “driving path to project completion.”

For more information, see the following links:

Article – Tracing Near Longest Paths with BPC Logic Filter

Video – Analyze the Near-Longest Paths in Microsoft Project using BPC Logic Filter

 

Problems with Driving Logic in Task Inspector and Task Paths (Microsoft Project 2010-2016)

Neither the Task Inspector nor the “Task Path” bar highlighter is a reliable indicator of task driving logic in Microsoft Project in the presence of mixed-type predecessor relationships or Backward Scheduling. 

At first glance, the Task Inspector pane in Microsoft Project (MSP) seems to be a reasonable tool for revealing the logic that is largely hidden in project schedules.  After all, you just select a task, click “Inspect Task”, and MSP provides a hyperlinked list of “Predecessor Tasks” that are controlling the schedule dates of the selected task.  For simple (i.e. Finish-to-Start) relationships between tasks with no progress, this assumption seems generally correct.

Unfortunately, many times Task Inspector is just plain wrong. (The examples below are taken from a ~1000-task real-world project schedule with actual progress updates.  Task names were obfuscated for confidentiality).  Each example represents many more cases in the schedule.

1. Once an actual start is recorded, logical drivers constraining the finish are ignored.

2. In case of parallel FS and SS driving predecessors, the FS driver is ignored.

Here is the corresponding bar highlighting from Task Path’s Driving Predecessors (MSP 2016).  The noted red bar should be orange like the one below it.

3. In case of parallel FS and FF driving predecessors, the FF driver is ignored.

3. In some (but not all) cases, an FF predecessor with substantial relative float is identified as the driving predecessor, while the true FS driver is ignored.

In general, the issues are present mainly in tasks with multiple predecessors of different types.  In forward scheduled projects, they are not found in tasks whose predecessors are all of type Finish-to-Start.

The “Driving Predecessors” bar highlighter of the Task Path tool in Microsoft Project Professional 2016 has the same issues as the Task Inspector results shown here.  They are both consistent with the StartDriver object for each task.  Any driving-logic tracer based on the StartDriver object – including those provided in my blog (Macro for Listing Driving Predecessors and QuickTrace Macros ) – has similar issues.

In the examples above, the task predecessors are displayed in Logic Inspector views from BPC Logic Filter (our MSP Add-in).  Predecessors are “driving” if their relative floats are zero; i.e. there is no working time between the corresponding predecessor and successor dates.  The driving predecessors identified in the examples are easily confirmed by examining the dates.  [Though illustrated mostly using Microsoft Project Professional 2010, all examples have been confirmed in Microsoft Project Professional 2016.]

Though not really highlighted here, it bears noting that MSP’s “driving logic” indicators are completely oblivious to resource-leveling decisions.  Thus, resource-driving logic is not addressed.  In contrast, BPC Logic Filter handles resource-driving logic quite well.

On Manually Scheduled Tasks [Aug’18 Edit]

If a manually scheduled task has predecessors, then MSP will identify one or more of them as the driving predecessor even when the manual scheduling has substantially delayed the task compared to the logic requirements.  This is one of the few factors differentiating a manually scheduled task from a normal (i.e. automatically scheduled) task with a mandatory constraint.  In this case, the Task Path “Driving Predecessors” bar highlighter ignores the delay and continues to trace “driving” logic through the identified start drivers.  (The Task Inspector suggests that the user either accelerate the task to remove the delay or convert the task to automatic scheduling.)  As a consequence, a schedule with manually scheduled tasks can have a driving path to project completion (according to Task Path) that is substantially different from the Critical Path that is based on Total Slack.

In Backward Scheduled Projects [Jan’19 Edit]

As pointed out in this recent article, neither the Task Inspector nor Task Path bar styles are useful in backward scheduled projects.